Summary: In the matter, on the Commission's Own Motion, to commence an investigation into the interconnection of independent power producers with a utility's system.

Industry: Electric

Company(s): Commission's Own Motion

Open Date: 10/24/2006

Order Dates: 10/24/2006, 2/27/2007

Click on the Document # to view the PDF file. A document # ending with an N, was not electronically filed or it has been deemed confidential. If you have questions, please contact the Michigan Public Service Commission at (517) 241-6170.

Document No. File Date Filed by On Behalf of Type Description Pgs
0143 10/7/2009 Baumann Cloverland Electric Cooperative Report Interconnection Report 2
0142 10/1/2009 Aaron Indiana Michigan Power Company Report I&M's Utility Interconnection Rpt 2
0141 9/30/2009 Christinidis The Detroit Edison Company Report The Detroit Edison Company Interconnection Report as required by the February 27 2007 Commission Order in MPSC Case No U-15113 8
0140 9/30/2009 Beyer Wisconsin Public Service Corporation Report Semi Annual Utility Interconnect Report 2
0139 9/30/2009 Beyer Upper Peninsula Power Company Report Semi Annual Utility Interconnect Report 2
0138 9/30/2009 Siepker Cherryland Electric Cooperative Report Interconnection Report September 2009 2
0137 9/30/2009 Rasmussen Northern States Power Company Report Semi-Annual Utility Interconection Report 2
0136 9/30/2009 Goodburne Alpena Power Company Report Interconnection Report 2
0135 9/29/2009 McQuillan Consumers Energy Company Report Interconnection Report in Compliance with February 27, 2007 Commission Order 9
0134 9/29/2009 Draba We Energies Report Bi-Annual Utility Interconnection Report 2
0133 9/25/2009 Szymoniak Presque Isle Electric & Gas Co-op Report Interconnection Filing Summary 2
0132 9/25/2009 Baumann HomeWorks Tri-County Electric Cooperative Report Interconnection Report 2
0131 9/24/2009 Baumann Ontonagon County Rural Electrification Association Report Interconnection Report 2
0130 9/23/2009 Baumann Midwest Energy Cooperative Report Interconnection Report 2
0129 9/22/2009 Harrell Alger Delta Cooperative Electric Association Report Bi-Annual Interconnection Report - January 1, 2009 through June 30, 2009 2
0128 9/22/2009 Baumann Edison Sault Electric Company Report Interconnection Report 2
0127 9/21/2009 Johnson Great Lakes Energy Cooperative Report Interconnection Report 2
0126 9/16/2009 Braun Thumb Electric Cooperative Report Thumb Electric Cooperative's Bi-Annual Interconnection Filing 2
0125 4/2/2009 Siepker Cherryland Electric Cooperative Report March 31, 2009 Interconnection Report 2
0124 4/1/2009 Draba We Energies Report Utility Interconnection Bi-Annual Report 2
0123 4/1/2009 Ness Northern States Power Company Report NSPW Semi-Annual Interconnection Report 2
0122 3/31/2009 Baumann Midwest Energy Cooperative Report   2
0121 3/31/2009 Beyer Upper Peninsula Power Company Report UPPCO 2008 Interconnect Report 2
0120 3/31/2009 Beyer Wisconsin Public Service Corporation Report WPS-MI 2008 Interconnect Report 2
0119 3/31/2009 Baumann Edison Sault Electric Company Report   2
0118 3/31/2009 Johnson Great Lakes Energy Cooperative Report   2
0117 3/31/2009 Baumann Ontonagon County Rural Electrification Association Report   2
0116 3/30/2009 Christinidis The Detroit Edison Company Report The Detroit Edison Companys Interconnection Report 6
0115 3/30/2009 Harrell Alger Delta Cooperative Electric Association Report 2008 Bi-Annual Interconnection Report 2
0114 3/27/2009 Szymoniak Presque Isle Electric & Gas Co-op Report Interconnection Report 2
0113 3/27/2009 Curry AEP Indiana Michigan Power Co. Report Compliance Report 2
0112 3/26/2009 McQuillan Consumers Energy Company Report Interconnection Report in Compliance with February 27, 2007 Commission Order 7
0111 3/24/2009 Goodburne Alpena Power Company Report Interconnection Report 2
0110 3/24/2009 Baumann Cloverland Electric Cooperative Report Interconnection Report 2
0109 3/23/2009 Baumann HomeWorks Tri-County Electric Cooperative Report 2008 Report 2
0108 3/17/2009 Krause Thumb Electric Cooperative Report Bi-Annual Interconnection Filing 2
0107 10/8/2008 Johnson Great Lakes Energy Cooperative Report Interconnection Report 2
0106 10/3/2008 Szymoniak Presque Isle Electric & Gas Co-op Report Interconnection Report 1
0105 10/2/2008 Siepker Cherryland Electric Cooperative Report Utility Interconnection Report April 2008 through September 2008 2
0104 10/1/2008 Goodburne Alpena Power Company Report Interconnection Report 2
0103 10/1/2008 Baumann Edison Sault Electric Company Report Interconnection Report 2
0102 10/1/2008 Baumann Midwest Energy Cooperative Report Interconnection Report 2
0101 10/1/2008 Ernst Cloverland Electric Cooperative Report Interconnection Report 2
0100 9/30/2008 Beyer Upper Peninsula Power Company Response UPPCO Interconnection Response Filing 2
0099 9/30/2008 Beyer Wisconsin Public Service Corporation Response WPSC-MI Interconnection Response Filing 2
0098 9/30/2008 Curry AEP Indiana Michigan Power Co. Report Compliance Report 4
0097 9/30/2008 Baumann Ontonagon County Rural Electrification Association Report Interconnection Report 2
0096 9/30/2008 McQuillan Consumers Energy Company Report Interconnection Report in Compliance with February 27, 2007 Commission Order 8
0095 9/29/2008 Ness Northern States Power Company Report Semi-Annual Utility Interconnection Report 2
0094 9/29/2008 Christinidis The Detroit Edison Company Report Interconnection Report in Compliance with February 27, 2007 Commission Order 5
0093 9/25/2008 Harrell Alger Delta Cooperative Electric Association Report Interconnection Requests 2
0092 9/19/2008 Draba We Energies Report Bi-Annual Interconnection Report 2
0091 9/18/2008 Ernst HomeWorks Tri-County Electric Coop Report Bi-Annual Interconnection Filing 2
0090 9/15/2008 Krause Thumb Electric Cooperative Report Bi-Annual Interconnection Filing 2
0089 4/3/2008 Baumann Edison Sault Electric Company Report Interconnection Report 2
0088 3/31/2008 Baumann Midwest Energy Cooperative Report Interconnection Report 2
0087 3/31/2008 Beyer Upper Peninsula Power Company Report UPPCO Semi-Annual Utility Interconnect Report 2
0086 3/31/2008 Beyer Wisconsin Public Service Corporation Report WPSC Semi-Annual Utility Interconnect Report 2
0085 3/31/2008 Johnson HomeWorks Tri-County Electric Cooperative Report Interconnection Report 2
0084 3/31/2008 Johnson Presque Isle Electric & Gas Co-op Report Interconnection Report 2
0083 3/31/2008 Siepker, Jr Cherryland Electric Cooperative Report Interconnection Report October 2007 through March 2008 2
0082 3/28/2008 Draba We Energies Report Utility Interconnection Report 2
0081 3/28/2008 Curry AEP Indiana Michigan Power Co. Report Compliance Report 3
0080 3/28/2008 McQuillan Consumers Energy Company Report Interconnection Report in Compliance with February 27, 2007 Commission Order 5
0079 3/28/2008 Christinidis The Detroit Edison Company Report The Detroit Edison Company Interconnection Report 4
0078 3/27/2008 Baumann Cloverland Electric Cooperative Report Interconnection Report 2
0077 3/27/2008 Baumann Ontonagon County Rural Electrification Association Report Interconnection Report 2
0076 3/26/2008 Johnson Great Lakes Energy Cooperative Report Interconnection Report 2
0075 3/13/2008 Goodburne Alpena Power Company Report Interconnection Report 2
0074 3/5/2008 Ernst Alger Delta Cooperative Electric Association Report Interconnection Report 2
0073 2/20/2008 Krause Thumb Electric Cooperative Report Thumb Electric Cooperative Interconnection Filing 2
0072 11/6/2007 Ernst Cloverland Electric Cooperative Report Cloverland Interconnection Report 2
0071 10/22/2007 Ernst Alger Delta Cooperative Electric Association Report Interconnection Filing 2
0070 10/22/2007 Ernst Midwest Energy Cooperative Report Interconnection Filing 2
0069 10/18/2007 Ernst HomeWorks Tri-County Electric Cooperative Report Interconnection Report 2
0068 10/18/2007 Baatz Edison Sault Electric Company Report Utility Interconnection 2
0067 10/17/2007 Krzywiecki Presque Isle Electric & Gas Co-op Exhibits Interconnection 1
0066 10/9/2007 Krause Thumb Electric Cooperative Report Thumb Electric Cooperative Interconnection Filing 2
0065 10/5/2007 Ernst Great Lakes Energy Cooperative Report Great Lakes Bi-Annual Interconnection Report 2
0064 10/5/2007 Ernst Ontonagon County Rural Electrification Association Report Ontonagon September 2007 Interconnection Report 2
0063 10/4/2007 Siepker Cherryland Electric Cooperative Report Revised 2007 Utility Interconnection Report 2
0062 10/3/2007 Siepker Cherryland Electric Cooperative Report 2007 Utility Interconnection Report 2
0061 10/1/2007 Baldwin Operations & Wholesale Markets Division Report Appendix 2, Staff Report on Utility Interconnection Issues 137
0060 10/1/2007 Baldwin Operations & Wholesale Markets Division Report Appendix 1, Staff Report on Utility Interconnection Issues 83
0059 10/1/2007 Baldwin Operations & Wholesale Markets Division Report Staff Report on Utility Interconnection Issues 58
0058 9/28/2007 McQuillan Consumers Energy Company Report Interconnection Report in Compliance with February 27, 2007 Commission Order 4
0057 9/28/2007 Draba We Energies Report Utility Interconnection Report 2
0056 9/28/2007 Moyle Upper Peninsula Power Comapny Report Semi-Annual Utility Interconnect Report 2
0055 9/28/2007 Derricks Wisconsin Public Service Corporation Report Semi-Annual Utility Interconnect Report 2
0054 9/28/2007 Curry AEP Indiana Michigan Power Co. Report Semi-Annual Interconnection Report 3
0053 9/28/2007 Christinidis The Detroit Edison Company Report Interconnection Report 3
0052 9/27/2007 Goodburne Alpena Power Company Report Utility Interconnection Report 2
0051 9/24/2007 Donovan No. States Power Company Report Semi-Annual Utility Interconnection Report 2
0050 5/25/2007 Baldwin MPSC Report Staff Interim Report on Net Metering Issues 21
0049 2/27/2007   Press Release   2
0048 2/27/2007   Order Interconnection reports due by 9-30-07 and every 6 months thereafter, establishes work groups and requires report within 90 days on simplified approach for net metering , and commences rulemaking proceeding under Case No. U-15239 18
0047 1/31/2007 Schafer MPSC Report Staff Report On Utility Interconnection Issues 37
0046 1/25/2007 Ault Michigan Electric Utilities through MEGA Letter Supplemental Attachment to Utilities Response 5
0045 1/25/2007 Pratt Comments   4
0044 1/24/2007 Christinidis The Detroit Edison Company Other Supplemental Explanations in Response to Staff Inquiry along with Proof of Service 19
0043 1/24/2007 Ault Michigan Electric Utilities through MEGA Response Michigan Electric Utilities Response to Staff Questions 23
0042 1/24/2007 Curry AEP Indiana Michigan Power Co. Response Response to Staff Questions 9
0041 N       Comments Entered in wrong case  
0040 1/24/2007 Vitez ITC Holdings, Corp. Comments   4
0039 1/24/2007 Coon Comments   5
0038 1/24/2007 Alvarado Great Lakes Renewable Energy Association Comments   3
0037 1/23/2007 Straith Syndevco, Inc. Comments   2
0036 1/23/2007 Porter American Transmission Company Comments Policy Recommendation of American Transmission Company 3
0035 1/22/2007 D Alecy Comments   1
0034 1/22/2007 Bauer Comments   1
0033 1/17/2007 McDonald Comments   1
0032 1/17/2007 Wakeman Comments   1
0031 1/16/2007 Straith Syndevco, Inc. Comments   3
0030 1/12/2007 Dempsey Constellation NewEnergy, Inc. Petition Intervene of Constellation NewEnergy, Inc., with Proof of Service 7
0029 12/20/2006 Snyder Comments   3
0028 12/20/2006 Sirna Comments   1
0027 12/19/2006 Alvarado Great Lakes Renewable Energy Association Comments   37
0026 12/19/2006 Queen Northwestern Michigan College Comments   4
0025 12/19/2006 Coon Comments   2
0024 12/19/2006 Ault MEGA Comments Advisory Comments of Michigan Electric Industry on Electric Interconnection Procedures 7
0023 12/19/2006 Kirby Theka Associates, Inc. Comments   3
0022 12/19/2006 Weeks Comments Comments on Diffuculty of Interconnection Process 41
0021 12/19/2006 Marvin Robert C. Evans Comments   11
0020 12/19/2006 Wakeman S.U.R. Energy Systems, LC Comments   4
0019 12/19/2006 Appleyard Comments   4
0018 12/19/2006 Geerlings Scenic View Dairy LLC Comments   7
0017 12/18/2006 Stockhausen Comments   1
0016 12/18/2006 Sarver Comments   2
0015 12/18/2006 Smith Renewable Services, LLC Comments   4
0014 12/15/2006 Dickens Laker Schools Comments   6
0013 12/1/2006 Pirrone Comments   20
0012 11/29/2006 Ault Michigan Electric & Gas Association Report Revised Version of MEGA Electric Utilities Interconnection Report 9
0011 11/28/2006 Peters Michigan Electric Cooperative Association Report Interconnection Report on behalf of member co-ops 2
0010 11/28/2006 McQuillan Consumers Energy Company Report Interconnections Pursuant to the Procedures Approved in Case No. U-14088 8
0009 11/28/2006 Christinidis The Detroit Edison Company Report Interconnection Report, with Proof of Service 9
0008 11/28/2006 Ault Michigan Electric & Gas Association Report MEGA Electric Utilities Interconnection Report 9
0007 11/28/2006 Curry AEP Indiana Michigan Power Co. Report I&M Activity Report 2
0006 11/14/2006 Christinidis The Detroit Edison Company Report Report Concerning Laker School District Interconnection Process 16
0005 11/1/2006 Kraycsir Comments   1
0004 11/1/2006 Brown Comments   7
0003 10/26/2006 Phillips Comments   1
0002 10/24/2006   Press Release   1
0001 10/24/2006   Order Orders DTE to file report regarding Laker School District interconnection by 11-14-06 and schedules public meeting for 1-9-07 14